Why Finalize Report is unavailable
- Confirm project and date. Changing tabs does not reopen a finalized report.
- Save or remove staged entries; Finalize does not auto-save them.
- For a normal day, save labor with positive hours. Equipment alone is insufficient.
- For delivery only, save delivery photos and explicitly confirm no labor on site. No operational rows may remain.
- With no work and no delivery, use the calendar’s reasoned No Work action.
- Read the validation or access message. Ask the project administrator to check missing permissions.
Finalization confirms the six sections together. Tab checkmarks alone do not satisfy day-type requirements. After a connection failure, check the saved report before submitting again.