How do I use Project Delivery to prepare the next scope of work?

  1. Open Project Delivery, choose project and area, then a package.
  2. Read What needs attention first, the source date and the next action. Past forecast needs current confirmation; missing links do not mean on schedule.
  3. Use Edit owner / notes for package context. The package owner is distinct from an action owner and receives no access by being named.
  4. Review evidence, exact scope and activity, requirements and actions; review coverage before construction release.

Procurement progress, schedule and construction readiness remain separate. An award, completed P6 task or delivered shipment cannot by itself establish readiness. This assesses ongoing work, not a project-wide go/no-go or critical-path ranking. Access and actions depend on your existing project permissions.

Next: source imports, baseline review, CPR review board, or construction release.