- Propose required-on-site and planned award dates, fabrication/shipping durations and confidence, AFE reference, first cash-out and required AFE approval date, evidence and reason.
- Review and explicitly approve. The authenticated reviewer and time identify approval; existing assessments are not approved baselines.
- Maintain award and delivery forecasts/actuals and current lead times with evidence and a mandatory review note.
- Review shared AFE readiness separately. For target changes, propose and approve a new version.
Original approved snapshots remain available. Stale proposals cannot supersede a newer version; forecasts need review after revision. Seven calendar days without a forecast or AFE review triggers Review due. Editing package notes does not refresh that clock. This is an on-screen queue, not scheduled reminders. Actual delivery timing does not establish construction acceptance.