How do I assign resources in the 3-Week Look-Ahead?

Assigning Resources in 3WLA

The current published 3WLA has a Resources toggle for inline assignment. Draft and superseded revisions are read-only for dispatch.

  1. Open the project 3WLA and publish the reviewed draft with Approve All.
  2. Click 👥 Resources. Foremen can view; superintendents, managers, and admins can modify within their access.
  3. Click a current Gantt bar to open the assignment panel.
  4. Select Worker, Equipment, or Crew, then set the dates, exact work days, hours, and shift.
  5. Click Add Resource.

Crew input creates individual worker/equipment assignments after every member passes validation. Assignments made here also appear on the dispatch board and can prefill a worker's Solo Entry.

Back to Resource Planning