How do I save a weekly forecast without double-counting commitments?

Save the weekly cost forecast

  1. Select the project and week in Weekly Control.
  2. Review Financial Position, evidence, Forecast readiness and the automatic preview.
  3. Enter Remaining Uncommitted Cost: future cost not already in Actual Cost or Open Commitments.
  4. Explain remaining scope, quantities and assumptions.
  5. Choose Working while preparing or Reviewed after management review, then Save snapshot.
  6. Read Forecast at Completion and Forecast Variance with their authority labels.

Each save creates a new audited snapshot. The entered scenario stays Manual · Provisional; Reviewed records review without making incomplete source data final. Correct a forecast by saving a new explained snapshot, without adding committed costs again.