Finalize a delivery-only day
- Save delivery photos through Materials → Deliveries.
- Choose Confirm no labor and continue in the saved-delivery callout, or use the visible finalization guidance.
- Confirm Delivery only — no labor on site.
- Select the enabled Finalize Report.
Saved delivery evidence is required, but AI recognition need not finish first. This day cannot contain labor, equipment, material-use, subcontractor, production or activity rows; notes and documents are allowed. If work occurred, use a normal day.
The finalized report has the delivery-only label, zero labor and zero material usage. Its attestation is locked. Physical receipt processing remains separate; further delivery captures are blocked after finalization.