Example project

See the daily signals before the cost report arrives.

This sample project shows how TCC connects daily field reporting to productivity, variance and margin impact.

$5M project 4% margin erosion = $200,000
Daily report data

What the field captured today

The report records the operational inputs that create cost movement: labour, equipment, materials, production and notes.

Daily Site Report

Project: P26-042 — Highway Footbridge  ·  Date: April 22, 2026

11°C — Sunny
Prepared by: Site Superintendent
TCC v3.6

Today's Signals

Budget overrun — 1000 Site setup Cost to date $14,378 = 206% of $6,997 budget.
Budget overrun — 5010 Structural steel Cost to date $565,540 = 220% of $257,320 budget.
Productivity below plan — 6070 Steel structure Actual productivity 0.35 t/crew-hr vs plan 0.50 t/crew-hr (−30%).

Today's Summary

Labour: 55 h (4 workers) · Equipment: 15 h (1 unit) · Subcontractors: 20 h (1 firm)
Production: 500 m³ excavation and backfill · 500 LS earthworks · 500 m³ trench excavation

Today's Costs by Activity

Activity Budget Cost today Cost to date % consumed
5010 — Structural steel$257,320$0$565,540220%
2050 — Excavation and backfill$479,000$6,450$226,19047%
1000 — Site setup$6,997$300$14,378206%
6070 — Steel structure$22,927$1,950$12,43054%
1020 — Insurance and bonding$2,572$0$00%
1052 — Site fencing$100,000$0$00%
1460 — Site surveying$1,610$0$00%

Today's Productivity

Activity Planned productivity Crew-hours Output Actual productivity % of plan
2050 — Excavation and backfill8.33 m³/crew-hr45500 m³11.11 m³/crew-hr133%
5010 — Structural steel0.05 t/crew-hr80.4 t0.05 t/crew-hr95%
6070 — Steel structure0.50 t/crew-hr124.2 t0.35 t/crew-hr70%
1000 — Site setup0.01 hrs/crew-hr10

Labour

Worker Hours Activity Pay item Work package
Marc Tremblay15.0Excavation and backfillTrench excavationEarthworks
Louis Bergeron10.0Site setupMobilizationPreparation and mobilization
Éric Gagnon15.0Excavation and backfillTrench excavationEarthworks
Sophie Lachance15.0Excavation and backfillTrench excavationEarthworks
Cost signal

Productivity down 8%

Installed quantity trailed plan while labour and equipment hours stayed near the estimate.

Variance example

Unit cost +6.5%

The activity is still in progress, so the variance can be investigated before the month-end report.

Margin impact

$18,400 exposure

Small daily losses compound when the same crew pattern continues across the remaining quantity.

Timeline

How this becomes a month-end surprise

Day 1

Crew productivity down 8%

Day 4

Equipment idle waiting for materials

Day 7

Production behind estimate

Day 30

Cost report confirms variance